- Tour du Valat - https://tourduvalat.org/en/ -

Energy-saving at the Tour du Valat: an exemplary programme

Consistent with being a research centre for the conservation of Mediterranean wetlands, the Tour du Valat is also concerned about minimising its impacts on the natural environment. That is why, over the last few years, it has developed a veritable environmental management strategy, developed in three areas:

 

 

The Tour du Valat buildings, in the heart of the Camargue

 

 

 

Objective: Factor 4

It is in the framework of this third area that the Tour du Valat committed itself in 2008 to an ambitious work programme: reducing the energy consumption of its buildings and its CO2 emissions by 400%! A challenge that was far from easy to achieve due to the configuration of the premises: more than 3000 m2 of floor space in eight buildings dating from the mid-19th century to the 1950s, spread over several hectares, and originally heated by eight gas or oil-fired boilers.

Nourished by the experience of the Life Promesse project (see here opposite) carried out at another Camargue site involved in an innovative renovation programme, the Vigueirat Marshes, in 2008 the Tour du Valat started by performing an energy diagnosis of all its facilities and buildings.

The result was a heating energy consumption of nearly 200 kWh/m2/year, with 168 tons/year of CO2 emitted.

The Tour du Valat then developed an energy strategy based on the principles of the ‘negaWatt’ approach:

The implementation of these solutions was then carried out between 2009 and 2013, thanks to considerable financial support from:

The buildings were renovated using a three-pronged approach:

 

 

Thermal insulation from outside of the farmhouse’s north side with rice straw in 2013

 

 

 

A very positive outcome

The final outcome of the renovation proved to be very positive.

In terms of thermal efficiency, the Tour du Valat’s consumption for heating went from 196 kWh/yr/m² before the works (average 2006-2009) to 61 kWh/yr/m² for the winter of 2013-2014, i.e. a saving of 69%. If we compare the results for identical climatic conditions, the outcome remains very favourable, with a saving of 48%.

Concerning the economic assessment (carried out only for the buildings using the heating network, i.e. 90% of the Tour du Valat’s total heating consumption), the estimated gain since the boiler was set up is €88,000 , i.e. €22,000 per year on average, for a total investment cost of €907,000 including VAT. On the basis of these initial results, the estimated return-on-investment time (excluding public grants) for the boiler and heating network is 20 years, or 39 years if we factor in the investment made for insulation. After deducting all public grants, the return-on-investment time should be about 18 years. However, the inclusion in these calculations of the fuel oil that had to be used for two heating seasons due to incidents that occurred with the boiler, plus the fact that the insulation work was not finalised until year 3, mean that the savings should increase once the system is fully operational, with a consequent decrease in the return-on-investment time.

The environmental analysis is also encouraging because the use of biomass (forestry chippings) as fuel caused CO2 emissions to drop by 87% between 2009 and 2014, i.e. a result significantly better than the objective. Concerning nitrogen oxides (NOX), although weight-for-weight wood produces more of them than fuel oil, emissions were reduced by more than 25% due to the drastic reduction in fuel consumption.


 

Supplying of the main heater with wood chips

 

 

Promising results to be improved

This renovation work enabled the Tour du Valat to:

 

The keys to success: unfailing desire and setting up monitoring indicators

Above and beyond the figures, launching such a process requires unfailing desire by the project owner. In particular, it is essential to have a specialist project manager and a workforce skilled in the fields concerned. An assistant project manager can also be very useful. Internal communication is also required in order to fully inform colleagues, raise their awareness, and encourage energy-saving behaviour. Getting all the colleagues to adopt energy-sobriety, and assisting them in the process, is a major workload on a daily basis. Yet that aspect must not be neglected, because it is a precondition for the acceptance of the renovation undertaken, together with the performances of the facilities. And we were able to observe that, even in an organisation working in the environmental sector, it can take a long time for people to change their way of thinking!

The setting up of measuring (calories, water, temperature, etc.) and monitoring systems is indispensable for obtaining a continuous assessment of the facilities’ performances, and the savings achieved. It also makes it easier subsequently to transfer experience to other organisations interested in conducting such projects.

 

Obstacles encountered

While the overall assessment was largely positive, the renovation programme carried out at the Tour du Valat in the last few years ran into some obstacles during its implementation. In particular, we can mention:

 

Medium and long-term perspectives

Although the operational set-up phase is now over, the Tour du Valat does not consider the works programme to be finished. Three objectives have been set for the next few years: